Apple, Wistron, Foxconn and Inventec are building AI servers in Houston, Fort Worth and Katy. Here are the investments, jobs, incentives and open questions.

Quick Answer: Texas has become a leading U.S. location for assembling artificial intelligence servers. Apple has been shipping AI servers from a 250,000-square-foot Houston factory since October 2025, Wistron opened a 324,000-square-foot Nvidia supercomputer plant in Fort Worth in July 2026, and Foxconn and Inventec are expanding AI server sites in northwest Houston and Katy. Disclosed investment across the Wistron, Foxconn and Inventec projects exceeds $1.4 billion.

Why is AI hardware manufacturing coming to Texas?

Until 2025, nearly all of the servers that run large AI models were assembled in Asia. Two announcements changed the map. On February 24, 2025, Apple said it would open a 250,000-square-foot server factory in Houston as part of a pledge to invest more than $500 billion in the United States over four years, a commitment it later raised to $600 billion. On April 14, 2025, Nvidia said it would build AI supercomputers in the United States for the first time, working with Foxconn in Houston and Wistron in the Dallas-Fort Worth area.

Nvidia said at the time that it had commissioned more than 1 million square feet of manufacturing space across its Arizona chip operations and the two Texas supercomputer plants, that mass production at both Texas sites was expected to ramp within 12 to 15 months, and that it planned to produce up to $500 billion of AI infrastructure in the United States within four years through its partners. Governor Greg Abbott welcomed the two Texas facilities in a statement on April 15, 2025; that statement gave no dollar, square footage or job figures.

Media reports at the time tied Apple’s decision to tariffs on imports from China. Whatever the mix of motives, the result 19 months later is a cluster of plants in three Texas cities, each at a different stage.

Company Location Investment Size Jobs Latest status
Apple Houston Not disclosed; company says hundreds of millions 250,000 sq ft, with a second factory doubling the campus Thousands, per Apple Shipping servers since October 2025; training center opened August 2026
Wistron, site 1 Fort Worth, AllianceTexas More than $580 million 324,598 sq ft More than 500 hired; 1,000 targeted Opened July 2026; producing Nvidia systems
Wistron, site 2 Fort Worth, AllianceTexas More than $181 million 766,994 sq ft 254 required under abatement No opening date found
Foxconn and Ingrasys Northwest Houston $450 million 1 million sq ft on 100 acres 600 $71.9 million buildout filed for September 2026 to January 2027
Inventec Katy $251 million total; $48 million third phase 126,349 sq ft in third phase More than 2,300 Third phase due January 2027

What is Apple building in Houston?

Apple’s Houston plant makes the servers behind Apple Intelligence and the company’s Private Cloud Compute system. The original announcement targeted a 2026 opening, but TechRepublic reported that Apple began shipping servers from Houston by October 24, 2025, ahead of schedule. The servers had previously been built overseas and now go to Apple data centers across the United States. Chief Operating Officer Sabih Khan said at the time that capacity would expand in 2026. Foxconn is the manufacturing partner on the project, according to published reports.

Apple has not disclosed the factory’s address, cost or headcount. The original announcement said the factory would employ thousands, and in August 2026 the company said only that it had invested hundreds of millions of dollars in the facility. Chief Executive Tim Cook said the facility was set up in less than nine months.

The campus is growing. On February 24, 2026, Apple said it would begin producing the Mac mini later in the year at a new factory on the Houston site, the first time that product would be made in the United States, and that the new building would double the campus footprint. The company also said the Houston servers include logic boards made on site. As of Apple’s August 13, 2026 update, Mac mini manufacturing was still described as starting this year.

That August update marked the opening of a 20,000-square-foot Advanced Manufacturing Center inside the server facility, Apple’s second manufacturing training site in the United States after one in Detroit that opened in August 2025 and has helped nearly 1,000 people. The Houston center offers free training to small and medium-sized businesses. The opening drew Commerce Secretary Howard Lutnick, Senator Ted Cruz and Houston Mayor John Whitmire, among others. Apple also works with Houston City College on training and hiring, and a March 2026 report by Capital Analytics Associates said the company employs more than 13,000 people in Texas, most of them in Austin.

What did Wistron open in Fort Worth?

Wistron, a Taipei-based electronics manufacturer founded in 2001 with more than 63,000 employees, opened its first U.S. manufacturing plant at the AllianceTexas development in north Fort Worth in July 2026, with a ceremony on July 21. The 324,000-square-foot facility, called Wistron D1, is already producing Nvidia’s GB300 Grace Blackwell Ultra system and preparing for the next-generation Vera Rubin system, according to Nvidia. Nvidia founder and Chief Executive Jensen Huang attended and signed the first unit built there, along with Wistron Chairman Simon Lin and Hillwood Chairman Ross Perot Jr.

Nvidia said in August that the plant had created more than 500 jobs so far, with a target of 1,000 by the end of 2026, and that it was first designed as a digital twin using the company’s Omniverse software. Converge Digest reported planned output of tens of thousands of AI boards a month.

The investment figures vary by source. Hillwood, the developer of AllianceTexas, put the project at $761 million across two buildings totaling nearly 1.1 million square feet, with more than 800 full-time jobs. Nvidia describes Wistron’s U.S. commitment as $700 million. Hillwood’s breakdown assigns more than $580 million to the 324,598-square-foot building at 15200 Heritage Parkway and more than $181 million to a 766,994-square-foot building at 14601 Mobility Way. Both were originally expected to be operational by early 2026; the first opened in July, and no opening date has been published for the second.

What incentives did Fort Worth offer Wistron?

The Fort Worth City Council approved 10-year property tax abatements in June 2025 of up to 80% at the Heritage Parkway site and up to 60% at the Mobility Way site. KERA reported the estimated tax reduction for the company at $30.7 million over 10 years, with the city netting $10.6 million in new revenue, and that Fort Worth competed for the project with El Paso, Nashville and Fremont, California.

The agreements carry deadlines, according to Community Impact. For the first site, Wistron must reach a minimum taxable value of $411 million by January 1, 2027 and employ 634 people at an average salary of $63,000 by December 31, 2026. For the second, the thresholds are $164 million in taxable value and 254 full-time jobs at the same average salary by the same dates. Combined, that is 888 jobs. Each deadline allows one 12-month extension, and missing them forfeits the abatement. Denton County, where the second site is located, scheduled consideration of an amendment to its own abatement for that property in August 2026; the outcome could not be confirmed.

How large is Foxconn’s Houston footprint?

Foxconn, Nvidia’s other Texas partner, has assembled a large base in northwest Houston through purchases and leases. It bought 10 acres and a building in Harris County for about $33 million in late 2024. In 2025 its subsidiary Ingrasys acquired Fairbanks Logistics Park, a 100-acre site with four buildings totaling 1 million square feet; the seller, Dalfen Industrial, announced the sale on June 5, 2025. FreightWaves, citing the Financial Times, reported a price of $142 million, compared with the $90.6 million Dalfen paid in July 2023. Separately, TrendForce reported that Foxconn Assembly leased two Houston plants totaling 601,600 square feet for about $56.55 million over terms of roughly ten years.

The Greater Houston Partnership has described the Foxconn project as a $450 million investment creating 600 direct jobs with a $920 million economic impact. Work is continuing: a filing registered with the Texas Department of Licensing and Regulation on July 16, 2026 describes an office, production and breakroom project at the Fairbanks site for Ingrasys Technology USA, with an estimated cost of $71.9 million, 74,312 square feet, a September 1, 2026 start and a January 29, 2027 completion date.

Foxconn said in October 2025 that it would deploy humanoid robots running Nvidia software at the Houston plant, which makes AI servers for Nvidia, and Chairman Young Liu said the company would keep scaling AI server output in Texas, Wisconsin and California. In August 2026 Nvidia described Foxconn as building a Houston factory for Nvidia AI systems. No public confirmation of volume production there was found.

Who else is building AI servers in Texas?

Inventec, another Taipei-based manufacturer, is expanding in Katy, west of Houston. Covering Katy News, citing a state filing, reported in June 2026 that the company plans a $48 million, 126,349-square-foot third phase for AI server testing and assembly at its Colonial Parkway site, with construction starting in June 2026 and completion in January 2027. Greater Houston Partnership data cited in the same report put Inventec’s total expected investment at $251 million with more than 2,300 jobs and a $3.2 billion economic impact. The Katy site was announced in September 2025.

The Houston-area plants draw on an established industrial workforce. The region had nearly 240,000 manufacturing jobs as of December 2024, according to Bureau of Labor Statistics data cited by InnovationMap.

What are the open questions?

Several facts remain undisclosed or unsettled as of November 18, 2026.

Deadlines. Wistron’s abatement terms require 888 jobs across its two Fort Worth sites by December 31, 2026, and the larger second building has no published opening date. Nvidia’s original 12-to-15-month window for mass production at both Texas plants ran out around July 2026; Wistron met it, while Foxconn’s status is less clear.

Disclosure. Apple has not published a cost, address or job count for Houston, and the start of Mac mini production has not been confirmed. No state incentive, such as a Texas Enterprise Fund grant, was found for the Apple, Foxconn or Wistron projects.

Trade policy. Tariffs are both a reason for the plants and a cost. Apple said tariffs cost it $800 million in the June 2025 quarter, according to Capital Analytics Associates.

Scale. Nvidia said in August 2026 that its U.S. partner and supplier network spans 43 states and cited a Public First estimate that Nvidia-driven AI demand adds $485 billion to U.S. gross domestic product in 2026. How much of that production ultimately runs through Texas depends on how fast the second Wistron building and the Foxconn and Inventec expansions come online.

Brian’s Take

When I line these projects up side by side, the thing I notice first is how uneven the disclosure is. Wistron’s numbers are public down to the street address and the salary floor because a city council had to vote on an abatement. Apple, which has the best-known name on the list, has told us the square footage and very little else. I put more weight on the figures that someone had to defend in a public meeting.

The second thing I notice is the jobs math. Fort Worth is giving up an estimated $30.7 million in taxes over a decade for a project measured in the high hundreds of millions of dollars and 888 required jobs at a $63,000 average. That is a capital-heavy bargain, and the December 31 deadline will tell us how it is going.

What I take from the whole picture is that Texas is now a place where finished AI systems get assembled in this country, in Houston, Fort Worth and Katy, and that this happened in well under two years.

Frequently Asked Questions

Where are AI servers made in Texas?

In Houston, where Apple and Foxconn operate; in Fort Worth, where Wistron builds Nvidia systems at AllianceTexas; and in Katy, where Inventec is expanding.

When did Apple start shipping servers from Houston?

By October 24, 2025, ahead of its original 2026 target, according to TechRepublic.

How much is Wistron investing in Fort Worth?

Hillwood put the two-building project at $761 million. Nvidia describes Wistron’s U.S. commitment as $700 million.

How many jobs will the Wistron plant create?

Nvidia said more than 500 had been created by August 2026, with 1,000 targeted by year-end. The city abatements require 888 jobs across two sites.

Is the Mac mini being made in Houston?

Apple said in February 2026 that Mac mini production would begin later in the year at a new factory on its Houston site. A start has not been confirmed.

Sources and Further Reading

  1. Apple Opens Advanced Manufacturing Center in Houston, Apple Newsroom
  2. Apple Accelerates U.S. Manufacturing, With Mac mini Production Coming Later This Year, Apple Newsroom
  3. NVIDIA to Manufacture American-Made AI Supercomputers in US for First Time, NVIDIA Blog
  4. NVIDIA and Partners Build in America, for America, NVIDIA Blog
  5. Governor Abbott Welcomes NVIDIA Investment in Texas, Office of the Texas Governor
  6. Wistron to Invest $761M in AI Supercomputer Sites at AllianceTexas, Hillwood
  7. Officials Celebrate Opening of Alliance Manufacturing Plant, KERA News and Fort Worth Report
  8. Fort Worth City Council Approves Tax Abatement for Possible Electronic Manufacturing Plants, Community Impact
  9. Project Registration TABS2026025427, Texas Department of Licensing and Regulation
  10. Tech Giant Foxconn Creating 600 Jobs With $450M Houston Investment, FreightWaves
  11. Foxconn Leased Texas Plants to Expand AI Server Capacity, TrendForce
  12. Foxconn to Deploy Humanoid Robots at Houston AI Server Plant, Reuters
  13. Apple Starts Shipping AI Servers From Houston Factory, TechRepublic
  14. Apple Announces 250,000-Square-Foot Houston Factory, InnovationMap
  15. AI Manufacturing Expansion Positions Houston for Growth, Capital Analytics Associates
  16. Wistron Opens $700M Texas Plant, Converge Digest
  17. Inventec Plans $48 Million Phase 3 Expansion at Katy Facility, Covering Katy News