November 25, 2026
Wind turbines standing on dry West Texas plains under a blue sky

Photo: Sam LaRussa / Unsplash (Unsplash License)

Six of eight Stargate buildings in Abilene were delivered by September 2026. See the gigawatts, jobs, tax breaks and the status of other Texas Stargate sites.

Quick Answer

As of November 21, 2026, the Stargate campus in Abilene is an eight-building, roughly 4 million square foot site on about 1,100 acres with a planned 1.2 gigawatts of capacity. Oracle said on its September 10, 2026 earnings call that six of the eight buildings, representing 618 megawatts and 75% of capacity, had been delivered to its customer, and Crusoe has said it expects the campus to be complete by the end of 2026. Two other Texas Stargate sites, in Shackelford County (1.4 gigawatts) and Milam County (1.2 gigawatts), are under construction and not yet operating.

What Is the Stargate Campus in Abilene?

Stargate is the artificial intelligence infrastructure program that OpenAI, Oracle and SoftBank announced at the White House in January 2025 with a headline commitment of $500 billion and 10 gigawatts of computing capacity in the United States. Abilene is its flagship. When the research group Epoch AI surveyed all seven U.S. Stargate sites in April 2026, it was the only one running workloads.

The roles on the site are split among several companies. Crusoe is the developer and builder. Lancium supplied the land, the grid interconnection and site engineering. Oracle owns the computing hardware and operates it as part of Oracle Cloud Infrastructure. OpenAI is the user. Nvidia supplies the chips.

Crusoe began construction in June 2024. The first phase was two buildings with more than 200 megawatts. In March 2025 Crusoe announced six more, bringing the plan to eight buildings, about 4 million square feet and 1.2 gigawatts. Oracle puts the site at 1,100 acres.

What Are the Key Numbers?

Measure Figure Source and date
Buildings planned 8 Crusoe, March 2025
Planned power capacity 1.2 gigawatts Crusoe, March 2025
Buildings delivered 6 of 8 (618 megawatts, 75% of capacity) Oracle earnings call, September 10, 2026
Investment, buildings 1 through 8 $47 billion Development Corporation of Abilene
City property tax abatement 85% for 10 years Local reporting on the Lancium agreement

How Many Buildings Are Operating in November 2026?

The most recent company statement is from Oracle. On its fiscal 2027 first-quarter earnings call on September 10, 2026, Oracle said six of the eight Abilene buildings had been delivered to the customer, representing 618 megawatts and 75% of the campus total. Oracle also said it delivered 131,000 graphics processors at Abilene during the quarter. It did not give a date for the final two buildings.

Date Milestone Basis
June 2025 Oracle begins delivering Nvidia GB200 racks OpenAI
September 30, 2025 First phase announced live on Oracle Cloud Infrastructure Crusoe
May 2026 Buildings 3 and 4 operational Epoch AI estimate
September 10, 2026 Six of eight buildings delivered, 618 megawatts Oracle earnings call
About November 1, 2026 Buildings 7 and 8 operational Epoch AI estimate only; not confirmed by Oracle

The last row deserves care. Epoch AI’s tracker, updated November 1, 2026, lists the full campus as operational, but it labels the dates for the final two buildings as its own estimate. Crusoe said in March 2026 that it expected completion of the eight buildings by the end of 2026, later than the mid-2026 target in its 2025 announcement. The confirmed position is six buildings delivered as of September.

How Much Computing Power Is on the Site?

Crusoe has said each building is designed to run up to 50,000 Nvidia GB200 NVL72 systems on a single network fabric. Epoch AI estimates each building at about 103 megawatts of power for computing equipment, which lines up with Oracle’s 618 megawatts for six buildings. Epoch puts the finished campus at 824 megawatts of computing load, the equivalent of roughly 1.02 million Nvidia H100 chips. Those are outside estimates, not company disclosures.

The 1.2 gigawatt figure is total site power, including cooling. The 824 megawatt figure is the electricity reaching the computing hardware.

How Much Money Is Being Invested?

There is no single agreed figure. Early local coverage described a $3.5 billion project. The Development Corporation of Abilene now lists a $47 billion investment for buildings 1 through 8. Epoch AI’s independent estimate is $31.2 billion.

Oracle’s results show the scale of its spending across all sites. For the quarter reported September 10, 2026, Oracle posted revenue of $19.3 billion, up 30% from a year earlier and capital spending of $28.45 billion, or $17.97 billion net of customer prepayments. Free cash flow was negative by about $5.4 billion, and remaining performance obligations, the contracted revenue not yet recognized, stood at $664 billion.

How Many Jobs Does the Campus Create?

Construction employment is large and temporary. Crusoe reported about 2,000 people on site daily in March 2025 and expected nearly 5,000 with the expansion. An Oracle fact sheet from September 2025 cited more than 6,400 construction workers on site each day. Oracle’s campus page puts expected construction jobs at more than 9,000.

Permanent job figures vary widely:

  • 57 jobs: the commitment in the original 2021 incentive agreement between the Development Corporation of Abilene and Lancium, tied to a capital investment of $52.35 million and an incentive of up to $2.5 million.
  • 400 new direct jobs: the Development Corporation of Abilene’s figure for the eight-building campus, with at least 50 jobs anticipated per building.
  • About 1,000 jobs: Oracle’s estimate of project-supported jobs within two years after construction ends.
  • About 1,700 ongoing onsite jobs: the figure in Oracle’s September 2025 fact sheet.

What Tax Breaks Did Abilene Give, and What Does It Get Back?

The incentives predate Stargate. They were negotiated with Lancium and extend to companies that build on its land. The City of Abilene agreed to abate 85% of property taxes for the first 10 years, and Taylor County agreed to an 80% abatement, according to local reporting on the agreements.

Because the taxable value is so large, the remaining share is still significant. The Development Corporation of Abilene projects that all eight buildings will generate $22.6 million a year for the city and $18.0 million a year for Taylor County over 20 years. It says those amounts equal 32% of the city’s and 25% of the county’s budgeted property tax revenue. The corporation also estimates more than $4 billion in direct and indirect economic impact over 20 years.

The local costs are also documented. Public radio reporting in August 2026 found average rent in Abilene near $2,600 a month, up nearly 50% in a year according to Zillow data, and reported that Abilene Christian University had more than 100 incoming students without housing for the fall semester.

Where Does the Power Come From?

The campus has a 1.2 gigawatt connection to the ERCOT grid. Crusoe’s design also includes behind-the-meter battery storage and solar, and natural gas turbines for backup power. Oracle says the backup units are GE Vernova gas turbines, used in place of diesel generators.

Epoch AI’s review of satellite imagery found a 200 megawatt substation built in 2022 and expanded in 2024, and a 1 gigawatt substation that appeared complete by July 2026. It said the on-site power plant looked complete in March 2026. The Texas Observer has reported that the $500 million on-site gas plant is authorized to emit 1.6 million tons of greenhouse gases a year.

How Much Water Does the Cooling System Use?

The buildings use direct-to-chip liquid cooling in a closed loop that is filled once and recirculated, with no evaporative cooling. Oracle’s campus page says each building needs roughly 50,000 gallons of water a year for maintenance, less than a typical American household uses. An Oracle fact sheet from September 2025 gave a lower figure of about 12,625 gallons per building. Epoch AI counts 640 air-cooled chillers on the site.

The design has had problems. Press reports in March 2026 said winter weather disrupted parts of the liquid-cooling infrastructure and took several buildings offline for multiple days.

What Happened to the Planned Expansion?

In September 2025 OpenAI listed a potential 600 megawatt expansion near Abilene alongside its new sites. In March 2026, press reports said Oracle and OpenAI would not proceed with that lease, citing financing negotiations and the weather disruption. Oracle called reports of a setback incorrect and said the existing campus remained on schedule. The committed 1.2 gigawatts were not affected.

The land did not sit idle. On March 27, 2026, Crusoe announced a separate 900 megawatt campus in Abilene to support Microsoft: two buildings, a 900 megawatt behind-the-meter power plant, and a first building expected to be energized in mid-2027. That would bring Crusoe’s Abilene total to about 2.1 gigawatts. The Microsoft campus is a Crusoe project and is not part of Stargate.

What Is the Status of the Other Texas Stargate Sites?

OpenAI named two more Texas locations on September 23, 2025. Neither had any operating capacity in the latest tracking available.

Site Developer and plan Latest status
Abilene (Taylor County) Crusoe; 8 buildings, 1.2 gigawatts; Oracle hardware Operating; 6 of 8 buildings delivered as of September 10, 2026
Shackelford County (“Frontier”) Vantage Data Centers; 10 buildings, 1.4 gigawatts, 1,200 acres, more than $25 billion; Oracle hardware Under construction; shells of buildings 1 through 5 complete as of September 4, 2026
Milam County SB Energy (SoftBank); 1.2 gigawatt lease signed by OpenAI Under construction; steel and roofing on first building as of March 2026

What Is Being Built in Shackelford County?

Vantage Data Centers announced its Frontier campus on August 19, 2025: more than $25 billion, 1,200 acres, 10 data centers, 3.7 million square feet and 1.4 gigawatts, with liquid cooling and a closed-loop chiller system. Vantage said the project would employ more than 5,000 people across construction and operations. Oracle’s fact sheet says the site will run on a behind-the-meter gas microgrid.

Vantage originally scheduled delivery of the first building for the second half of 2026. Epoch AI’s satellite review dated September 4, 2026 found the shells of buildings 1 through 5 complete and roofed, and foundations underway for buildings 6 and 7. Epoch estimates the first building will be operational in August 2027 and the full campus in late 2028.

What Is Being Built in Milam County?

The Milam County site, near Burlington about 70 miles northeast of Austin, follows a different model. SB Energy, a SoftBank Group company, builds and operates the campus and its power infrastructure, and SoftBank rather than Oracle owns the hardware, according to Epoch AI. On January 9, 2026, OpenAI and SoftBank each invested $500 million in SB Energy, and OpenAI said it had signed a 1.2 gigawatt lease for the initial buildout.

Epoch AI recorded land clearing from September 2025 and steel framing and roofing on the first building in March 2026. Its tracker, last updated in May 2026, projects the campus fully operational by the end of 2028.

Brian’s Take

What stands out to me is the distance between the announcement numbers and the delivered numbers, and how quickly that distance is closing in Abilene. A site that broke ground in June 2024 had six buildings and 618 megawatts in a customer’s hands by September 2026. That is real steel, power and hardware in Taylor County, not a press release.

I would also read the jobs and tax numbers with clear eyes. The same campus is described as 57 jobs, 400 jobs, 1,000 jobs or 1,700 jobs depending on the document, and the city gave up 85% of the property tax for a decade to get it. The remaining 15% is still projected at $22.6 million a year for the city, which shows the size of the asset. Meanwhile rents near $2,600 a month land on residents who do not share in the upside.

The dropped 600 megawatt expansion is the detail I find most useful. It shows these plans are not fixed. In this case the land went to a Microsoft project within weeks. For Texas business, the lesson is that the power-ready site is the scarce asset, and the tenant can change.

Frequently Asked Questions

Is the Abilene Stargate campus finished?

Not confirmed. Oracle said on September 10, 2026 that six of eight buildings had been delivered. Crusoe has targeted the end of 2026 for completion, and Epoch AI estimates the last two buildings became operational around November 1, 2026, but Oracle has not announced it.

Who owns and runs the Abilene site?

Crusoe built it on Lancium land. Oracle owns and operates the hardware, and OpenAI is the user.

How many permanent jobs will there be?

The Development Corporation of Abilene cites 400 new direct jobs. Oracle expects about 1,000 project-supported jobs within two years of completion, and an earlier Oracle fact sheet cited about 1,700 ongoing onsite jobs.

Are the Shackelford County and Milam County sites operating?

No. Both were under construction in the latest available tracking. Outside estimates put first operations at Shackelford in 2027 and full buildout of both sites in 2028.

Sources and Further Reading

  1. Crusoe Expands AI Data Center Campus in Abilene to 1.2 Gigawatts, Crusoe, March 18, 2025
  2. Crusoe Announces New 900 MW AI Factory Campus in Abilene, Crusoe, March 27, 2026
  3. Abilene, Texas Data Center campus page, Oracle
  4. Oracle and OpenAI Data Center Fact Sheet, Oracle, September 2025
  5. Five New Stargate Sites, OpenAI, September 23, 2025
  6. Stargate and SB Energy partnership announcement, OpenAI, January 9, 2026
  7. OpenAI Stargate Abilene, Shackelford and Milam data center tracker entries, Epoch AI, 2026
  8. OpenAI Stargate: Where the US Sites Stand, Epoch AI, April 17, 2026
  9. Oracle Q1 Strong and So Is Capital Expenditures, Constellation Research, September 10, 2026
  10. Project Radiance: Powering the Future of AI in Abilene, Texas, Development Corporation of Abilene
  11. Vantage Data Centers Unveils Plans for Frontier, a $25B Mega-campus in Texas, Vantage Data Centers, August 19, 2025
  12. Abilene Stargate housing report, KUT News, August 12, 2026
  13. Oracle and OpenAI Scrap Planned 600MW Abilene Expansion, Tom’s Hardware, March 10, 2026
  14. Texas Standard report on Stargate construction in Abilene, January 26, 2026
  15. Texas Observer report on the Abilene Stargate natural gas plant
  16. New Energy Company Renegotiates the Deal with Abilene, local news report syndicated by AOL