Quick Answer: On November 9, 2026, the U.S. Nuclear Regulatory Commission issued a construction permit for four X-energy Xe-100 reactors at Dow’s Seadrift complex in Calhoun County, the first advanced nuclear plant authorized at a U.S. industrial site. Texas has also closed applications for its $350 million Texas Advanced Nuclear Development Fund, while a test reactor in Lockhart reached criticality in August and a four-unit AP1000 application near Amarillo remains in federal review. No Texas advanced reactor has a final construction commitment yet.
What did federal regulators approve in Texas on November 9?
The Nuclear Regulatory Commission granted a construction permit to Long Mott Energy, a wholly owned subsidiary of Dow, for the Long Mott Generating Station in Calhoun County. The plant would sit at Dow’s UCC Seadrift Operations site on the Gulf Coast. The permit covers four Xe-100 high-temperature gas-cooled reactors designed by X-energy. Each unit is rated at 80 megawatts of electricity or 200 megawatts of heat, for a combined output of up to 320 megawatts electric.
The plant’s main product is not grid power. According to the NRC, the primary output is high-temperature industrial steam for the Seadrift complex, with surplus electricity sent to the grid. The reactors are meant to replace aging energy and steam assets at the site and to supply the complex for about 60 years.
Why is the Long Mott permit considered a first?
The NRC listed several firsts in its announcement. It is the agency’s first construction permit for a high-temperature gas-cooled reactor in nearly 60 years, its first approval of a multimodule advanced reactor facility, its first approval of a pebble-bed core, and its first approval of a design that refuels while operating. The U.S. Department of Energy, which supports the project through its Advanced Reactor Demonstration Program, called it the first advanced nuclear facility authorized for construction at a U.S. industrial site.
How long did the federal review take?
Dow submitted the application in March 2025. The NRC issued an environmental assessment with a finding of no significant impact in May 2026 and released its final safety evaluation on October 30, 2026, which the agency said was one month ahead of schedule. The permit followed ten days later, inside the 18-month timetable the NRC had set.
| Long Mott Generating Station | Detail |
|---|---|
| Permit holder | Long Mott Energy, a Dow subsidiary |
| Location | Dow UCC Seadrift Operations, Calhoun County |
| Reactors | Four X-energy Xe-100 units |
| Rating per unit | 80 MW electric or 200 MW thermal |
| Total electric output | Up to 320 MW |
| Construction permit | November 9, 2026 |
| Preliminary investment decision | Expected in 2027 |
| Targeted first energy delivery | Early 2030s |
Does the permit mean the Seadrift reactors will be built?
No. The permit authorizes construction only. Long Mott Energy needs a separate NRC operating license before it can load fuel or run the reactors, and Dow has not made a final decision to build. World Nuclear News reported that the company must first finish engineering and design and take the project to its board of directors, and that a preliminary investment decision is expected in 2027. Construction could then begin later this decade, with startup early in the next.
Dow has said the decision will turn on competitiveness, execution readiness and capital affordability.
What makes the Xe-100 different from the reactors already running in Texas?
The four reactors operating in Texas today are large pressurized water units. The Xe-100 is a small helium-cooled design that runs on TRISO fuel, in which particles of high-assay low-enriched uranium are sealed inside graphite pebbles that circulate through the core. That allows fuel to be added while the reactor runs. The design’s expected emergency planning zone is about 400 meters, compared with 10 miles for conventional light-water reactors, which is what makes siting inside a chemical complex practical.
The fuel plant is also advancing. X-energy’s TRISO-X subsidiary completed vertical construction of its TX-1 facility in Oak Ridge, Tennessee, in September 2026, according to the Energy Department.
How does Texas’ $350 million nuclear fund work?
House Bill 14, signed in June 2025 after passing the Texas House 134 to 9 and the Senate 26 to 5, created the Texas Advanced Nuclear Energy Office and the Texas Advanced Nuclear Development Fund. Lawmakers appropriated $350 million. The office adopted its rules in March 2026 and opened applications on April 1.
The money is split by statute between two reimbursement programs. Both pay back up to half of qualifying costs after they are incurred, and neither covers overhead or other indirect costs.
| Feature | Construction Reimbursement Program | Project Development and Supply Chain Program |
|---|---|---|
| Allocation | Up to $280 million (80%) | Up to $70 million (20%) |
| Cap per project | Lesser of 50% of qualifying costs or $120 million | $12.5 million, up to 50% of qualifying costs |
| Federal licensing test | NRC construction permit or license application docketed by December 1, 2026 | No docket requirement |
| Application deadline | May 14, 2026 | May 14, 2026 |
| Funds must be committed by | August 31, 2027 | August 31, 2027 |
| Grant periods end by | August 31, 2029 | August 31, 2029 |
Who can qualify for the construction money?
The construction program is the larger pot and the narrower door. It is limited to electric generation or nuclear fuel cycle facilities located in Texas that have an NRC application on the docket. Projects holding only Energy Department authorization do not qualify. When the fund opened in April, the office’s director said only two projects met the docketing test, and trade reports identified them as the Dow and X-energy plant at Seadrift and Fermi America’s AP1000 project in the Panhandle.
The arithmetic is tight. With a $120 million ceiling per project, $280 million can cover two maximum awards and leave $40 million. Abilene Christian University’s research reactor also has a docketed NRC permit, but Nuclear News reported that it is excluded from the construction program because the project had already received $120 million in other state funding. It remains eligible for the smaller program, where a $12.5 million cap means $70 million would stretch across at least six projects if each received the maximum.
Has Texas announced the awards?
Not in any public record reviewed for this article. The office’s guidance said the first grant period could begin as early as September 14, 2026, and that it expected to award its full appropriation in this round. As of November 18, 2026, the fund’s web page states that the requests for applications are closed and lists no recipients or award amounts. The office plans to report to the Legislature in January 2027, Power magazine reported. A third program authorized by House Bill 14, a completion bonus for finished plants, received no funding in the 2026-2027 state budget.
Which other reactor projects are moving in Texas?
The Seadrift permit is the most advanced commercial milestone, but it is one of several active tracks. Some projects are going through the NRC, while others are using an Energy Department pilot program that authorizes test reactors outside the NRC process.
| Project | Texas location | Size | Latest verified status |
|---|---|---|---|
| Long Mott (Dow, X-energy) | Seadrift, Calhoun County | 4 units, 320 MW electric | NRC construction permit, November 9, 2026 |
| Project Matador (Fermi America) | Amarillo area | 4 AP1000 units, 4.4 GW electric | Partial application docketed; draft environmental statement issued September 30, 2026 |
| MSR-1 (Natura Resources, Abilene Christian University) | Abilene | 1 MW thermal | NRC construction permit, September 2024; coolant salt delivered September 18, 2026 |
| Groves Isotope Test Reactor (Oklo) | Lockhart, Caldwell County | 15 MW thermal | First criticality reported August 6, 2026 |
| PWR-5 pilot (Last Energy) | Texas A&M-RELLIS, Bryan | 5 MW | Under construction; awaiting Energy Department authorization as of July 2, 2026 |
Where does Fermi America’s Amarillo project stand?
Fermi America has applied for a combined license to build and operate four Westinghouse AP1000 reactors totaling 4.4 gigawatts at its Project Matador campus beside the Pantex plant near Amarillo. The NRC accepted the first two parts of the application for docketing on September 5, 2025. The site-specific third part has not been filed. The agency’s project page, updated November 10, 2026, shows a target of June 30, 2027, for a revised safety analysis and October 31, 2027, for the third part, with a full review schedule to be set by December 15, 2027. Safety evaluation and decision dates are not yet set.
The environmental track is further along. Fermi is part of an NRC pilot in which the applicant prepares the environmental impact statement. The draft was issued September 30, 2026, the 45-day public comment period ends November 23, and the final statement is targeted for December 2026. As of March 2026, the company’s plan called for the first unit to operate in 2031 or 2032 and the other three between 2034 and 2036.
What happened at the test reactors in Lockhart, Abilene and Bryan?
Oklo’s Groves Isotope Test Reactor in Lockhart, south of Austin, reached criticality in early August 2026. Nuclear News reported it was the fifth reactor to do so under the Energy Department’s Reactor Pilot Program and the first on private land, less than a year after work began on a greenfield site. The water-cooled unit is a test platform for future isotope production reactors.
In Abilene, Natura Resources and Abilene Christian University are building MSR-1, a 1-megawatt-thermal reactor that dissolves its fuel in molten fluoride salt. The university holds an NRC construction permit issued in September 2024, and Natura agreed in December 2025 to pursue Energy Department authorization as well. On September 18, 2026, the department delivered more than 4,700 pounds of fluoride coolant salt recovered from a 1960s Oak Ridge experiment.
Austin-based Last Energy is building a 5-megawatt pilot reactor at the Texas A&M-RELLIS campus in Bryan. As of July 2, 2026, it had not reached criticality and was waiting on Energy Department authorization; later status could not be confirmed for this article. The Texas A&M System signed agreements with four developers in February 2025 for RELLIS projects exceeding 1 gigawatt combined.
How large is nuclear power in Texas today?
Texas has two nuclear plants with four reactors and a little more than 5 gigawatts of capacity: Comanche Peak in Somervell County, at about 2,400 megawatts, and the South Texas Project in Matagorda County, at about 2,645 megawatts. The state’s Advanced Nuclear Reactor Working Group put their contribution at about 10% of ERCOT energy in its November 2024 report. Texas 2036, citing ERCOT data, puts it at 8% and ranks Texas seventh among states for nuclear generation in 2025.
Against that base, the four Seadrift reactors would add roughly 6% to the state’s nuclear capacity. Fermi’s four AP1000 units would nearly double it, although that project is planned to serve a private campus.
Why is the state paying for this now?
Demand is the stated reason. Power magazine reported in April 2026 that ERCOT projected peak demand climbing from 87 gigawatts in 2025 to 145 gigawatts in 2031, a 67% increase, with data centers responsible for more than 24 gigawatts of the growth. The working group report behind House Bill 14 also made an industrial case, citing a University of Texas study that estimated, in a mid-range scenario, an average of 148,000 jobs a year, $50.6 billion in new economic output and $27.3 billion in worker income if Texas became a manufacturing base for small reactors.
What should Texas businesses watch next?
Several dated milestones lie ahead. The comment period on Fermi’s draft environmental statement closes November 23, 2026, with the final statement targeted for December. December 1, 2026, is the cutoff for projects to have a docketed NRC application under the state construction program. The Texas Advanced Nuclear Energy Office is due to report to lawmakers in January 2027. State grant funds must be committed by August 31, 2027. And Dow’s preliminary investment decision on Seadrift, also expected in 2027, will show whether an industrial customer commits capital to the project.
Frequently Asked Questions
How much power would the Seadrift reactors produce?
Four Xe-100 units at 80 megawatts each would supply up to 320 megawatts of electricity. Each can alternatively deliver 200 megawatts of heat as industrial steam.
When could the Seadrift reactors start operating?
Dow expects a preliminary investment decision in 2027. If the project proceeds, construction could start later this decade, with first energy in the early 2030s after an NRC operating license.
How much has Texas set aside for advanced nuclear projects?
The Legislature appropriated $350 million to the Texas Advanced Nuclear Development Fund: up to $280 million for construction reimbursement and up to $70 million for project development and supply chain reimbursement.
Has any new reactor started up in Texas?
Yes, at test scale. Oklo’s Groves Isotope Test Reactor in Lockhart reached criticality in early August 2026 under Energy Department authorization. No new commercial power reactor is under construction.
Sources and Further Reading
- NRC Issues First Construction Permit in Nearly 60 Years for High-Temperature Gas-Cooled Reactor, News Release 26-083, U.S. Nuclear Regulatory Commission
- Dow, X-energy Receive Construction Permit for Advanced Nuclear Project in Texas, U.S. Department of Energy
- NRC Issues Construction Permit for Dow/X-energy Long Mott Project, Nuclear News, American Nuclear Society
- US Issues Landmark Construction Permit for Texas SMR Plant, World Nuclear News
- Texas Advanced Nuclear Development Fund Request for Applications FAQs, Texas Advanced Nuclear Energy Office
- Governor Abbott, TANEO Boost Advanced Nuclear Construction, Office of the Texas Governor
- Texas Opens $350M in Nuclear Funding, Nuclear News, American Nuclear Society
- Texas Opens $350M Advanced Nuclear Grant Programs, POWER magazine
- Fermi America Combined License Application, Units 1-4, U.S. Nuclear Regulatory Commission
- Fermi Expands Texas Energy Campus, Nuclear Engineering International
- Oklo’s Isotope Test Reactor Achieves Criticality, Nuclear News, American Nuclear Society
- The Deadline Arrives: Checking In on the Reactor Pilot Program, Nuclear News, American Nuclear Society
- Department of Energy Provides Rare Salt Material to Natura Resources, U.S. Department of Energy
- Texas Advanced Nuclear Reactor Working Group Report, Public Utility Commission of Texas
- Texas’ Reliable Nuclear Power Generation, 2000-2025, Texas 2036