Texas holds $3.3 billion in federal BEAD broadband funds, yet signed awards total $1.07 billion for 208,873 locations and payments were put on hold in August.

Quick Answer: Texas holds the largest federal Broadband Equity, Access and Deployment (BEAD) allocation of any state, $3,312,616,455, but its approved plan commits only about $1.26 billion of that to construction. Signed grant agreements announced in June 2026 totaled $1,067,572,758 across 17 providers and 208,873 locations, and a follow-up re-award covering more than 27,000 additional locations won federal approval on Oct. 15, 2026. As of Nov. 17, 2026, no project payments are publicly known to be flowing: the state placed a hold on BEAD disbursements in August, and an audit of the broadband office is still open.

How much broadband money does Texas actually have?

The headline number and the working number are far apart. The National Telecommunications and Information Administration (NTIA) assigned Texas $3,312,616,455 under BEAD, the broadband program created by the 2021 federal infrastructure law. The Texas Broadband Development Office (BDO), which sits inside the Comptroller of Public Accounts, administers it.

NTIA’s summary of the Texas final proposal lists total deployment cost at $1,257,675,573. The remainder, $2,054,940,883, is labeled cost savings from the “Benefit of the Bargain” round, the single bidding round Texas ran after NTIA restructured the program in June 2025. That restructuring made the program technology neutral and shifted scoring toward cost, which opened the door to satellite and fixed wireless bids that the original fiber-first rules had disfavored.

The construction budget in the approved plan equals about 38% of the federal allocation. What happens to the unspent balance has not been fully settled at the federal level. NTIA’s September 2026 notice directs part of the savings nationwide toward a supplemental round for locations the first pass missed, and defers other uses to later guidance.

Key fact Figure
Federal BEAD allocation to Texas $3,312,616,455
Total deployment cost in approved plan $1,257,675,573
Cost savings from Benefit of the Bargain round $2,054,940,883
Provider match, total $595,140,965
Eligible locations in plan 242,903
Average BEAD cost per location $5,178
Signed subgrantee agreements 17 providers, $1,067,572,758, 208,873 locations
Post Award Change re-award 8 subgrantees, more than 27,000 locations

Sources: NTIA final proposal overview (November 2025); BDO award list as reported by Telecompetitor (June 2026); BDO program page (updated Nov. 6, 2026).

How many Texas locations will be connected, and with what technology?

The plan NTIA reviewed covers 242,903 eligible broadband serviceable locations: homes, businesses and community anchor institutions that are unserved (below 25/3 megabits per second) or underserved (below 100/20). The Comptroller’s office said in November 2025 that the plan touches all 254 counties and would let almost every Texas location on the federal broadband map connect to high-speed service.

Fiber takes barely half. That is a sharp change from the program’s original design, and it is the main reason the bill came in so far under the allocation.

Technology Locations Share of locations
Fiber to the premises 122,994 50.6%
Low Earth orbit satellite 65,901 27.1%
Fixed wireless (licensed and licensed-by-rule) 54,008 22.3%
All technologies 242,903 100%

Source: NTIA BEAD final proposal overview for Texas, updated Nov. 18, 2025. NTIA noted the data were subject to change pending final federal review.

When was the plan approved?

The BDO took public comment on a draft from Oct. 13 to Oct. 22, 2025, and submitted it to NTIA on Oct. 27, 2025. The Comptroller’s office and NTIA announced approval on Nov. 20, 2025; the BDO’s program page lists Dec. 4, 2025, as the final proposal approval date. The original plan selected 22 applicants to serve more than 240,000 locations and more than 2,700 community anchor institutions, backed by $1.2 billion in federal grant funds and $177 million in state match, according to the BDO.

Which providers won Texas BEAD awards?

Seventy entities applied in the July 2025 bidding window and requested $6.4 billion, according to an analysis of BDO data reported by Telecompetitor. SpaceX applied for 244,596 locations, nearly the entire eligible map, and Nextlink Internet for 204,846.

In early June 2026 the BDO announced signed agreements with 17 providers. The final list, as compiled by Telecompetitor from the state’s award file, follows.

Provider Technology Final award Locations
4 IP Technology and Media (Nexstream) Fiber and fixed wireless $401,831,807 32,404
Lyte Fiber Fiber and fixed wireless $115,992,900 9,666
SpaceX (Starlink Services) Low Earth orbit satellite $108,787,903 63,887
Plains Internet Fiber $96,116,680 13,055
Frontier Southwest / Verizon Fiber $59,185,393 8,259
Aristotle Unified Communications Fiber $56,914,449 10,795
Charter Communications (Spectrum) Fiber $47,810,536 7,830
AMG Technology Investment Group (Nextlink Internet) Fixed wireless $42,161,852 34,417
USConnect Holdings (Livingston Telephone) Fiber $36,634,389 3,928
AT&T Services (Southwestern Bell) Fiber $32,196,465 6,653
Connect Holding II (Brightspeed) Fiber $24,396,727 6,574
360 Broadband Fiber $16,071,631 2,716
Rural Telecommunications of America Fiber $15,803,008 3,314
Valor Telecommunications of Texas (Uniti) Fiber $4,778,788 2,403
Lucky Fiber Fiber $4,469,117 1,447
IBT Group USA Fixed wireless $2,300,708 1,264
VTX Communications Fiber and fixed wireless $2,120,407 261

Who got the most money, and who got the most locations?

Those are two different companies. Nexstream holds the largest award by dollars, $401.8 million, or roughly 38% of the signed total, for 32,404 locations. That works out to about $12,400 per location. SpaceX holds the most locations, 63,887, or about 31% of the signed total, for $108.8 million, roughly 10% of the dollars and about $1,700 per location. Nextlink’s fixed wireless award is cheaper still per location, about $1,225 across 34,417 sites.

Fiber means trenching or stringing cable to each address, while satellite and fixed wireless need far less ground construction, which helps explain the spread.

Why did the awards shrink between the plan and the contracts?

Provisional awards totaled $1,271,233,725 for 240,205 locations. The signed contracts came to $1,067,572,758 for 208,873 locations, a drop of about $203 million and 31,332 locations, or roughly 13% of the eligible sites, according to Telecompetitor’s comparison and Broadband Breakfast’s reporting.

Five provisional winners did not appear on the final list:

  • Astound Broadband, $166,100,901
  • Resound Networks, $23,127,233
  • Thrive Broadband, $1,483,986
  • AMA Communications, $1,385,518
  • Amazon Kuiper Commercial Services (Amazon Leo), $1,145,659

Four of those rescinded their awards, the BDO said. Astound told Broadband Breakfast it had filed 33 applications designed as one contiguous fiber route, but only five were approved, leaving separate builds far from its network that it considered financially unworkable. Its approved projects would have covered more than 16,000 locations. Resound’s award covered about 15,500 locations; the company did not explain its decision. Amazon’s award, for 2,014 satellite locations, was reported in June as still awaiting a signature.

What happened to the 31,000 dropped locations?

In June 2026 the BDO ran what it calls a Special Process, open to subgrantees with executed agreements, to re-award locations released by preliminary winners. It selected eight subgrantees to serve more than 27,000 locations and community anchor institutions. The state submitted that Post Award Change to NTIA on Sept. 21, 2026, and NTIA approved it on Oct. 15, 2026. The BDO’s program page now lists program funding at $1.3 billion in BEAD funds and $187 million in state match. The page reviewed for this article does not itemize the re-awards by provider or say how many released locations remain unassigned.

What is the status of the buildout as of November 2026?

The BDO had said it expected construction to begin as soon as summer 2026. That did not happen on schedule, for reasons that have more to do with politics and oversight than engineering.

  1. June 2026: At a state Senate committee hearing, lawmakers questioned BDO Director Bryant Clayton about a change to the payment schedule for low Earth orbit satellite providers. Other providers were to receive 10% up front with the balance paid in tiers. Clayton said the schedule was changed for satellite providers days before the awards at the request of the governor’s office, according to The Texas Tribune. The governor’s office has denied favoritism, Broadband Breakfast reported.
  2. July 21, 2026: Lt. Gov. Dan Patrick and House Speaker Dustin Burrows jointly called for an audit of the BDO.
  3. Aug. 1, 2026: Don Huffines was sworn in as comptroller, succeeding Acting Comptroller Kelly Hancock. He then announced an internal review of the agency, including the BDO.
  4. Aug. 10, 2026: A hold on all BEAD disbursements took effect, to last until further notice, according to an email to subgrantees obtained by The Texas Tribune. No reason was given.
  5. Sept. 3, 2026: NTIA released its BEAD Supplemental Deployment Policy Notice, creating a second round for unserved locations that were previously ineligible.
  6. Oct. 15, 2026: NTIA approved the Texas Post Award Change.
  7. Nov. 6, 2026: NTIA issued the supplemental eligible location list and lengthened the challenge window from 30 to 45 days.

In the sources reviewed for this article, there was no public announcement that the disbursement hold has been lifted or that the audit has concluded. The BDO’s program page, last updated Nov. 6, 2026, does not mention the hold. Patrick and Burrows have said the Legislature will act when its next session begins in January 2027.

What comes next?

The BDO says the supplemental round’s challenge process begins Dec. 14, 2026, when it publishes the eligible location list. That process runs 45 days with no rebuttal period, followed by a second Benefit of the Bargain round and a Supplemental Deployment Plan submitted to NTIA. The Benton Institute estimates the supplemental process will add nine months or more to BEAD timelines nationally. A public BEAD Location Progress Map is expected in early 2027. Once work starts, awardees have four years to serve every eligible location, with progress reporting and clawback provisions attached.

What is the Texas Broadband Infrastructure Fund?

The Broadband Infrastructure Fund (BIF) is the state’s own money. Voters created it by approving Proposition 8 in November 2023, with an initial $1.5 billion investment. Its effective period runs from 2024 to 2035. According to the BDO, it pays for 9-1-1 upgrades, the pole replacement program and state matching funds for BEAD, among other uses.

State-run program Amount What it covers
BOOT Round II $623.4 million awarded 61,185 residential, 18,250 business and 2,191 anchor locations
BOOT Round I $10.4 million awarded 1,468 residential, 77 business and 15 anchor locations; due Dec. 31, 2026
Texas Pole Replacement Fund $75 million from BIF Reimburses 50% of eligible costs or $5,000 per pole, whichever is less

Bringing Online Opportunities to Texas (BOOT) draws on $634.8 million from the federal Capital Projects Fund, of which Texas received $500.5 million, plus BIF money. It is separate from BEAD.

Brian’s Take

As a former investment manager and analyst, I read budgets against results, and the gap here is the story. Texas was handed $3.3 billion and has a plan that spends about $1.26 billion of it. Lower cost per location is a real achievement on paper. But a year after federal approval, the number that matters most to a rural business owner, locations actually connected with BEAD dollars, is one the state has not yet published.

The per-location math also deserves a clear look. Roughly $1,700 a site for satellite against about $12,400 for the largest fiber award is a big spread, and both can be reasonable for the terrain involved. What I would want as a taxpayer or a bidder is a payment schedule that applies the same way to everyone, or a plain explanation when it does not. That question, not the technology, is what drew the audit calls in July.

For Texas contractors, equipment suppliers and rural employers, my read is that the calendar is now the main risk. An open audit, a disbursement hold with no end date in the public record, a legislative session in January and a federal supplemental round starting in December all sit ahead of the first shovel. I would plan around that uncertainty rather than around the original summer 2026 start.

Frequently Asked Questions

How much BEAD money did Texas receive?

NTIA allocated Texas $3,312,616,455, the largest amount of any state. The approved final proposal lists $1,257,675,573 in deployment cost, with $2,054,940,883 recorded as savings.

How many Texas locations are covered?

The final proposal covers 242,903 eligible locations. Signed agreements announced in June 2026 covered 208,873, and a re-award approved Oct. 15, 2026, added more than 27,000.

What share of Texas BEAD locations will get fiber?

Under the approved plan, 50.6% (122,994 locations) get fiber to the premises, 27.1% (65,901) get low Earth orbit satellite and 22.3% (54,008) get fixed wireless.

How much did Starlink receive in Texas?

SpaceX’s Starlink Services signed for $108,787,903 to serve 63,887 locations, the most locations of any provider. Nexstream received the most money, $401,831,807.

Has BEAD construction started in Texas?

The BDO expected construction as soon as summer 2026. A hold on BEAD disbursements took effect Aug. 10, 2026, and the sources reviewed show no public notice that it has ended as of Nov. 17, 2026.

Sources and Further Reading

  1. BEAD Final Proposal Overview: Texas, National Telecommunications and Information Administration
  2. Broadband Equity, Access and Deployment (BEAD) Program page, Texas Comptroller Broadband Development Office
  3. Broadband Funding programs page, Texas Comptroller Broadband Development Office
  4. Bringing Online Opportunities to Texas (BOOT) Program page, Texas Comptroller Broadband Development Office
  5. Federal Government Approves Texas Broadband Development Office’s $1.3 Billion BEAD Proposal (Nov. 20, 2025), Texas Comptroller of Public Accounts
  6. How Texas’ Final BEAD Subgrantee Contracts Compare With Provisional Awards, Telecompetitor
  7. Texas Benefit of the Bargain Round: $6.4B Requested by 70 Providers, Telecompetitor
  8. Winning Bidders Back Out of 31,000 BEAD Locations in Texas, Broadband Breakfast
  9. Astound Explains $165 Million BEAD Refusal in Texas, Broadband Breakfast
  10. Texas Halts BEAD Disbursements as New Comptroller Recasts Broadband Office, Broadband Breakfast
  11. Texas broadband office pauses funds disbursement (Aug. 12, 2026), The Texas Tribune
  12. Texas broadband funding favoritism allegations (July 28, 2026), The Texas Tribune
  13. Texas Pauses BEAD Disbursements After Allegations It Favored Starlink, Fierce Network
  14. The Buildout: Hawaii to Start BEAD Builds as Texas Stalls, Light Reading
  15. NTIA Opens a Second Round of BEAD Funding for Locations the Program Missed the First Time, Benton Institute for Broadband and Society