November 25, 2026
Close-up of rows of cooling fans on high-density computing hardware

Photo: Andrey Matveev / Unsplash, Unsplash License.

Texas bitcoin miners become AI landlords: Riot's $28 billion Corsicana lease, Core Scientific's colocation surge and ERCOT data on mining's shrinking share.

Quick Answer: The companies that made Texas the center of U.S. bitcoin mining spent the third quarter of 2026 turning themselves into landlords for artificial intelligence. Riot Platforms leased its entire Corsicana campus, 910 megawatts, to an unnamed AI lab for about $28 billion over 15 years, Core Scientific drew more than 92% of its revenue from colocation, and Cipher Digital booked its first high-performance computing rent. ERCOT’s latest survey shows facilities that mine virtual currency now account for less than 1% of the capacity asking to connect to the grid.

Texas bitcoin miners built their business on warehouses of specialized machines, in towns such as Rockdale and Corsicana, that run hard when electricity is cheap and shut off when it is not. The third-quarter 2026 reports these companies issued between October 27 and November 9 show how quickly that identity is fading. Mining revenue fell at every large operator that reported, while lease revenue from AI and high-performance computing (HPC) tenants appeared or multiplied.

How did Texas bitcoin miners perform in the third quarter of 2026?

The common thread was a lower bitcoin price. Riot Platforms reported an average production value of $70,855 per bitcoin, down from $114,361 a year earlier. MARA Holdings put the average price of the bitcoin it mined at $71,688, a drop of 37.4%. That fed directly into revenue. Riot’s mining revenue fell to $116.0 million from $160.8 million even though it produced 16% more bitcoin. MARA’s total revenue fell 34.9% to $164.2 million, of which $159.0 million came from mining. Cipher Digital’s mining revenue dropped to $20.8 million from $71.7 million, and Core Scientific’s self-mining revenue shrank to $12.3 million from $57.4 million.

Net income figures need careful reading, because several were driven by accounting gains rather than operations. Core Scientific reported net income of $1.18 billion, of which $1.03 billion was a non-cash gain on the fair value of warrants. Cipher’s $31.6 million profit included a $127.2 million non-cash warrant gain; its operating loss widened to $71.9 million. MARA’s $634.4 million profit rested on fair-value gains on digital assets and bitcoin receivables that The Block put at nearly $885 million. Riot earned $4.0 million, compared with $104.5 million a year earlier.

Company Q3 2026 revenue Bitcoin mining revenue Net income AI and HPC position
Riot Platforms $181.4 million $116.0 million $4.0 million 1,151 MW leased; about $38 billion contracted
MARA Holdings $164.2 million $159.0 million $634.4 million No leases signed as of Nov. 9
Core Scientific $232.9 million $12.3 million (self-mining) $1.18 billion 485 MW billing; $215.4 million colocation revenue
Cipher Digital $26.7 million $20.8 million $31.6 million $5.9 million first HPC rent; $9.1 billion contracted at Barber Lake
Galaxy (data centers segment) $79.1 million leasing revenue Not reported $323 million (whole company) 133 MW delivered to CoreWeave at Helios

What is Riot Platforms doing at Corsicana and Rockdale?

Riot delivered the quarter’s largest single announcement. In its November 4 release, the company said it had signed a 15-year, triple-net powered land lease covering the whole of its Corsicana campus with a tenant it identified only as a leading frontier AI lab. The lease covers 910 megawatts of critical IT capacity on a contiguous 332-acre parcel. Riot values the contract at about $28 billion over the initial term, or about $1.8 billion a year on average including escalators, and about $54 billion if the tenant exercises both five-year extensions.

How does the Corsicana lease work?

Riot is not building a finished data center. It delivers powered pads, and the tenant builds on them. The company estimates total capital at $6 million per IT megawatt, or $5.5 billion, which it describes as roughly half the cost of a typical Tier 3 build. Riot pays $2 million per megawatt for site work and electrical infrastructure. The other $4 million per megawatt is reimbursed to the tenant in phases once each phase is delivered and paying rent, and Riot expects to fund those reimbursements with non-recourse project debt sized to the contracted rent. Rent is owed on the full 910 megawatts whatever the tenant’s utilization, and power is passed through to the tenant.

Corsicana lease term Detail
Capacity 910 MW critical IT on 332 acres
Initial term and value 15 years; about $28 billion
Value with both extensions About $54 billion
Phase 1 400 MW, September 2027
Phase 2 200 MW, January 2028
Phase 3 310 MW, July 2028
Rent start No later than 60 days after each powered pad delivery
Capital $6 million per MW; $5.5 billion in total

The same AI lab signed a lease at Rockdale earlier in 2026, though the release does not give its size or terms. Together with a contract with AMD, Riot says it has now leased 1,151 megawatts of critical IT capacity, worth about $38 billion in long-term contracted revenue, and expects average annual net operating income above $2 billion at full deployment. Subtracting Corsicana leaves 241 megawatts and roughly $10 billion for the Rockdale and AMD agreements combined.

What is left of Riot’s mining business?

Mining is still most of Riot’s revenue today. The company produced 1,637 bitcoin in the quarter. Its cost to mine one bitcoin was $39,265 excluding depreciation but $78,805 including it, which is above the $70,855 average value of the coins produced. The data center segment brought in $18.4 million, including $7.7 million of base rent in the first full quarter after 25 megawatts were delivered to AMD. The engineering segment, which builds custom electrical equipment in Denver and Houston, more than doubled revenue to $47.0 million on demand from third-party data centers.

Riot is paying for the conversion with its bitcoin. It has sold 20,264 bitcoin in 2026 for about $1.5 billion, mainly to fund data center development, and held 2,418 at September 30 alongside $748.2 million in cash.

How far along are Core Scientific, Cipher and Galaxy?

Has Core Scientific stopped being a bitcoin miner?

Nearly. Core Scientific, which lists four of its 11 facilities in Texas, reported on November 5 that colocation revenue reached $215.4 million, up almost 60% from the second quarter and more than 14 times the $15.0 million of a year earlier. Self-mining contributed $12.3 million and hosted mining $5.2 million. The company was billing 485 megawatts at September 30, up from 395 megawatts at June 30, and says it is repurposing its remaining mining facilities for colocation as circumstances allow. An Earnings Whispers review of the results said the self-mining business ran at a negative 61% gross margin and is slated for a full exit by year-end.

The shift is expensive. Capital spending was $985.1 million in the quarter, long-term debt stood at $4.30 billion and the company carried a stockholders’ deficit of $1.09 billion. The same review said a roughly $6 billion project-bond financing for a buildout for AMD, including a Pecos site due in the first half of 2027, had not yet been secured.

What did Cipher Digital report?

Cipher Digital, which trades on Nasdaq as CIFR, is earlier in the same transition. Total revenue fell 62.8% to $26.7 million, according to Benzinga’s account of the November 2 business update. The $5.9 million of HPC leasing revenue, recognized after rent began at its Black Pearl site, was the company’s first. Interest expense rose to $59.0 million from $1.3 million as long-term borrowings climbed to $5.45 billion from $2.71 billion at the end of 2025.

What Cipher has is contracts and a queue position. It amended the lease at its Barber Lake data center in Texas with an unnamed AI laboratory to add a second 10-year term, lifting total contracted revenue at the site to about $9.1 billion, including about $5.2 billion of new rental commitments. It sold $850 million of zero-coupon convertible notes due 2032 to support the project. Its Colchis site in Texas received a conditional base-load classification for 1 gigawatt in ERCOT’s Batch Zero process, plus conditional studied-load classifications for another 1.6 gigawatts. Cipher has also begun developing natural gas pipelines that could support up to 2.5 gigawatts of on-site generation and counts a development pipeline of about 5.9 gigawatts.

How much of Galaxy’s Helios campus is leased?

Galaxy’s Helios campus, a Texas site The Block has described as once among North America’s largest bitcoin mines, is the furthest along in generating rent. Galaxy said on October 27 that all 133 megawatts of critical IT load delivered so far went to CoreWeave by the end of the second quarter, making the third quarter the first full quarter of revenue-generating operations for the first phase of Helios I. Data center leasing revenue was $79.1 million, and the segment’s adjusted gross profit rose to $79 million from $20 million in the prior quarter.

Galaxy completed $3.5 billion of senior secured notes to fund the second phase of Helios I, where data hall deliveries are scheduled to begin in the second quarter of 2027. Helios II, with 830 megawatts of approved capacity, is not yet under lease; the company says it is in discussions with prospective tenants.

Where does MARA stand?

MARA is the holdout, still overwhelmingly a miner. It produced 2,247 bitcoin in the quarter and ended September with an energized hash rate of 71.2 exahashes per second, up from 60.4 a year earlier, according to an SEC-API.io analysis of its quarterly filing. The company describes about 1.9 gigawatts of energized capacity across nearly 20 sites on four continents and a path to roughly 4.8 gigawatts.

Its AI plans are real but unsigned. Joint ventures with Starwood target more than 1 gigawatt of initial IT capacity, yet no leases had been signed as of November 9. In Texas, MARA holds rights to as much as 2,000 megawatts in Matagorda County, a project that sits in ERCOT’s Batch Zero study and carries up to $600 million in milestone payments, none of which has been paid. Its Granbury site hosts AI inference without material revenue so far.

MARA also reworked its balance sheet. It held 34,012 bitcoin at September 30, then sold 13,597 after quarter-end for about $1.1 billion and repaid $750 million of bitcoin-backed loans in full. Its board authorized a share buyback of up to $500 million on November 9.

What does ERCOT data show about miners and large loads?

ERCOT’s own figures confirm that mining is now a small slice of new demand. In a preliminary summary presented to the Public Utility Commission on November 5, the grid operator reviewed 429 loads requesting 177.4 gigawatts of interconnection capacity. Only 22 of those facilities reported virtual currency mining as a full or partial function, and 20 of the 22 were smaller than 75 megawatts. Facilities with no mining accounted for 175.9 gigawatts, leaving about 1.5 gigawatts tied to mining. ERCOT noted that the price-responsive behavior of mining has operational implications for the system. Its final report is targeted for December 10.

What is Batch Zero and why does it matter to miners?

Batch Zero is ERCOT’s one-time transitional study of large loads, defined as 75 megawatts or more. Conditional classifications released September 3 placed 204 projects totaling 66.4 gigawatts in the base-load category and 158 projects in the studied-load category, which one slide put at 127.9 gigawatts and another at 125.4 gigawatts. A further 373 projects totaling 302.2 gigawatts were excluded. On August 3, after Governor Abbott directed a verification and audit of data centers moving through interconnection, ERCOT paused the study and paused energization approvals for data centers and crypto mining facilities of 75 megawatts or more. Final inclusion decisions are expected in December. Cipher’s Colchis classifications and MARA’s Matagorda rights both depend on the outcome.

How much do miners earn by curtailing power?

Riot, which takes part in ERCOT and MISO demand response programs, recorded $24.7 million of power curtailment credits in the quarter, about $15,067 per bitcoin mined, down from $30.6 million a year earlier. For the first nine months, credits rose to $55.7 million from $46.7 million.

Frequently Asked Questions

Which Texas bitcoin miner has the largest AI lease?

Riot Platforms. Its Corsicana lease covers 910 megawatts and is valued at about $28 billion over 15 years.

Is Core Scientific still mining bitcoin?

Barely. Self-mining produced $12.3 million of its $232.9 million in third-quarter revenue, and an Earnings Whispers review said a full exit is planned by year-end.

Who is the tenant at Galaxy’s Helios campus?

CoreWeave, which has received 133 megawatts of critical IT load. Another 830 megawatts approved for Helios II is not yet leased.

How much of ERCOT’s requested load is crypto mining?

About 1.5 gigawatts of 177.4 gigawatts in ERCOT’s November 5 preliminary summary, or less than 1%.

Sources and Further Reading

  1. Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights, Riot Platforms
  2. Core Scientific Announces Third Quarter 2026 Results, Core Scientific (Business Wire)
  3. Galaxy Announces Third Quarter 2026 Financial Results, Galaxy Digital (PR Newswire)
  4. MARA Announces Third Quarter 2026 Results, MARA Holdings (GlobeNewswire)
  5. MARA Holdings Q3 2026 Earnings SEC Filing Analysis, SEC-API.io
  6. MARA Posts $634 Million Q3 Net Profit on Bitcoin Gains, The Block
  7. Cipher Digital’s Revenue Plunges, but Its AI Data Center Ambitions Are Growing, Benzinga
  8. Cipher Digital Reports $27 Million in Q3 Revenue as HPC Leasing Begins, Finviz
  9. Core Scientific Third Quarter 2026 Earnings Review, Earnings Whispers
  10. Galaxy Profit Jumps 1,500% in Record Quarter, The Block
  11. Batch Zero Update, Board of Directors Meeting, September 14-15, 2026, ERCOT
  12. Data Center State and Community Impact Request for Information: Preliminary Summary, ERCOT